May Update
Works are progressing well with substantial developments being made over the recent months. Please see below a list of completed and upcoming works.
April 2024 progress:
• Scum channels & pool surround slabs complete
• Flat roofing progressed in the period and is nearing completion.
• Pool hall roofing progressed in the period
• Intumescent paint substantially complete with soffit spraying progressing
• Internal masonry substantially complete with external masonry progressing
• SFS substantially complete to Zone 1 with the pool hall also progressing in the period
• Curtain walling substantially complete to Zone 1 with internals & pool hall to commence imminently
• Cladding continued in the period
• Commenced internal partitions
Upcoming works:
• Complete intumescent paint & soffit spraying
• Continue works to flat roofs, sports hall roof and achieve watertight milestone for pool hall roof works
• Continue external masonry to sports hall and Zone 1
• Complete SFS & curtain walling to pool hall
• Commence asbestos removal in preparation for demolition to the existing centre
• Continue internal works with M&E & partitions