June Update
Throughout June the progression of work has been substantial, external brickwork is progressing and internally the schedule is moving along as planned. Please see below a list of completed and upcoming works.
June 2024 Progress:
- Flat roofing & cappings progressed further in the period
- Pool Hall Roof Acoustic Board & VCL completed and roof sheets lifted on ready for install
- Internal Masonry Complete
- SFS Complete
- Curtain Walling installed to the pool hall
- Long span cladding completed
- Continued internal Partitions & MEP to GF and Level 1
- Render commenced
- Tiling to commence
- Screed to pools completed
- Mist coating commenced
- West gable brickwork due to complete in the month
Upcoming works in July:
- Wet change wall tiling.
- Completion of pool hall roof and continue external masonry
- Commencement of pool tiling
- Continue internal works with M&E & Partitions
- Continuation of decorations
- Completion of sub-station works
Recent Comments