Throughout June the progression of work has been substantial, external brickwork is progressing and internally the schedule is moving along as planned.  Please see below a list of completed and upcoming works.

June 2024 Progress: 

  • Flat roofing & cappings progressed further in the period  
  • Pool Hall Roof Acoustic Board & VCL completed and roof sheets lifted on ready for install
  • Internal Masonry Complete
  • SFS Complete
  • Curtain Walling installed to the pool hall
  • Long span cladding completed
  • Continued internal Partitions & MEP to GF and Level 1 
  • Render commenced
  • Tiling to commence
  • Screed to pools completed 
  • Mist coating commenced
  • West gable brickwork due to complete in the month

 

Upcoming works in July:

  • Wet change wall tiling.
  • Completion of pool hall roof and continue external masonry
  • Commencement of pool tiling
  • Continue internal works with M&E & Partitions
  • Continuation of decorations
  • Completion of sub-station works